Which Knowledge Area involves identifying the people, groups, or organizations that may be impacted by or impact a project?

Which Knowledge Area involves identifying the people, groups, or organizations that may be impacted by or impact a project?
A . Project Risk Management
B . Project Human Resource Management
C . Project Scope Management
D . Project Stakeholder Management

Answer: D