Which key step must be done prior to the final switchover to ensure all backups are present on the target?

After completing the initial root-to-root system migration, you are ready to switch over to the new target system. You have been performing some critical backups of key systems during this initial replication phase.

Which key step must be done prior to the final switchover to ensure all backups are present on the target?
A . Perform a final catchup replication
B . Perform all required DNS changes
C . Run an MCS flush on the target
D . Run an MCS flush on the source

Answer: C