Exam4Training

Which item should be excluded from the testing scope?

A consultant has been working with a university to build a new student services solution using Salesforce. The consultant is preparing for User Acceptance Testing.

Which item should be excluded from the testing scope?
A . User experience in production
B. Large data volumes
C. Data load simulation
D. Average versus peak performance

Answer: A

Exit mobile version