Which is the purpose of the Change theme?
A . Prevent change to baselined products
B . Identify, assess and control any potential and approved changes to baselined products
C . Establish mechanisms to monitor and compare actual achievements against those planned
D . Assess and control uncertainty
Answer: B
Explanation:
The purpose of the Change theme in PRINCE2 is to establish a clear, structured approach for identifying, assessing, and controlling changes to baselined products. This theme ensures that only approved changes are implemented, helping to manage and minimize their potential impacts on the project’s objectives.
Reference: PRINCE2 Foundation manual, PRINCE2 official resources