Which is the Issue Register NOT used for?

Which is the Issue Register NOT used for?
A . Capture external events that are impacting a stage
B . Record information about a deviation in stage tolerance
C . Capture any threats or opportunities that might have an impact on a stage
D . Record any problems identified when authorizing a Work Package

Answer: A

Explanation:

The Issue Register in PRINCE2® is used to capture and record all issues that may affect the project but it is not designed to capture external events unless they become issues directly impacting project deliverables or processes. Its primary function is to log problems identified in project execution, not general external events.

Reference: PRINCE2® Foundation official study guide and online resources.