Which is often used during a retrospective to capture lessons?
A . A Glad! Sad! Mad! board
B. A Kanban board
C. A burn chart
D. A Gantt chart
Answer: A
Explanation:
Reference: https://publications.axelos.com/prince2agile2016/content.aspx?page=pra_120&showNav=t rue&expandNav=true