Which is often used during a retrospective to capture lessons?

Which is often used during a retrospective to capture lessons?
A . A Glad! Sad! Mad! board
B . A Kanban board
C . A burn chart
D . A Gantt chart

Answer: A

Explanation:

Reference: https://publications.axelos.com/prince2agile2016/content.aspx?page=pra_120&showNav=true&expandNav=true