Which is NOT represented by one of the three primary categories of stakeholder identified in PRINCE2?
A . Those with a financial interest in the project
B . Those who will manage the project on a day-to-day basis
C . Those who will specify the desired outputs of the project
D . Those who will create the project’s outputs
Answer: A
Explanation:
PRINCE2® identifies three primary categories of stakeholders: 1) those who will specify the desired outputs (customers/users), 2) those who will manage the project on a day-to-day basis (suppliers), and 3) those who use the project’s outputs. Those with a financial interest in the project are not explicitly categorized as one of the primary stakeholder types in PRINCE2®.