Which is NOT represented by one of the three primary categories of stakeholder identified in PRINCE2?

Which is NOT represented by one of the three primary categories of stakeholder identified in PRINCE2?
A . Those with a financial interest in the project
B . Those who will manage the project on a day-to-day basis
C . Those who will specify the desired outputs of the project
D . Those who will create the project’s outputs

Answer: A

Explanation:

PRINCE2® identifies three primary categories of stakeholders: 1) those who will specify the desired outputs (customers/users), 2) those who will manage the project on a day-to-day basis (suppliers), and 3) those who use the project’s outputs. Those with a financial interest in the project are not explicitly categorized as one of the primary stakeholder types in PRINCE2®.

Reference: PRINCE2® Foundation official study guide and materials.

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments