Which is NOT one of the PRINCE2 integrated elements?
A . Tailoring PRINCE2 to the project environment
B . The processes
C . The products
D . The themes
Answer: C
Explanation:
In the context of PRINCE2, the integrated elements include the principles, themes, processes, and tailoring PRINCE2 to the project environment. ‘The products’ are not listed as one of these integrated elements. Instead, they are outputs or deliverables that result from applying the PRINCE2 methodology to project management.
Reference: PRINCE2 Foundation manual, PRINCE2 official resources