Exam4Training

Which is NOT included in the PRINCE2 definition of a project?

Which is NOT included in the PRINCE2 definition of a project?
A . A project is a temporary organization
B . A project’s purpose is to deliver one or more business products
C . A project is part of ‘business as usual’
D . A project is based on an agreed Business Case

Answer: C

Explanation:

According to PRINCE2, a project is not considered part of ‘business as usual’. The defining attributes of a project include it being a temporary organization that is created for a specific purpose, which contrasts with ‘business as usual’ that involves ongoing, routine activities within an organization.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources

Exit mobile version