Which is NOT an industry-recognized methodology for quantifying critical delay?

Which is NOT an industry-recognized methodology for quantifying critical delay?
A . Gantt Chart.
B . Periodic Windows.
C . Collapsed As-Built.
D . Time Impact.

Answer: A