Which is not a mandatory event in Scrum but a mandatory event in Nexus?

Which is not a mandatory event in Scrum but a mandatory event in Nexus?
A . Cross-Team Refinement
B. Sprint Retrospective
C. Sprint Review
D. Daily Scrum

Answer: A

Explanation:

In Scrum, Product Backlog refinement is not a mandatory event, but it is a strongly recommended practice. In Nexus, refinement (officially called as Cross-Team Refinement) is mandatory.