Which is MOST LIKELY to trigger premature closure of a programme?
Which is MOST LIKELY to trigger premature closure of a programme?
A . The scope of one of the key projects has been changed
B . There is a change of senior responsible owner
C . The programme is no longer aligned with corporate strategy
D . The last tranche has been completed as per the programme plan
Answer: C