Which is assumed to be a customer’s responsibility in the PRINCE2 customer/supplier environment?

Which is assumed to be a customer’s responsibility in the PRINCE2 customer/supplier environment?
A . Specify the desired result
B . Provide the resources and skills to deliver the desired result
C . Ensure the technical integrity of a project
D . Develop a project’s products

Answer: A

Explanation:

In the PRINCE2 customer/supplier environment, it is typically the customer’s responsibility to specify the desired result of the project. This responsibility involves defining what the project should achieve in terms of outcomes and benefits, aligning with the customer’s business objectives.

Reference: PRINCE2® Foundation official study materials.