Which is an objective of the Closing a Project process?
A . Prepare the plan for the next stage
B . Assess any benefits that have already been realized
C . Produce a Benefits Review Plan to identify what benefits are expected
D . Check that all benefits are realized before closing a project

Answer: C

Explanation:

One of the objectives of the Closing a Project process is to produce a Benefits Review Plan. This plan

outlines how the benefits of the project will be measured and reviewed after the project has been closed. It is crucial for ensuring that the benefits expected from the project are tracked and assessed in the post-project phase.

Reference: PRINCE2® Foundation official study guide and materials.