Which is an objective of the Closing a Project process?

Which is an objective of the Closing a Project process?
A . Review and approve the plan for project closure
B . Review the performance of the project against its baseline
C . Perform any post-project reviews
D . Create a Benefits Review Plan

Answer: B

Explanation:

The objective of the Closing a Project process in PRINCE2 includes reviewing the performance of the project against its baseline. This ensures that all objectives have been achieved, the project has delivered the required products, and stakeholders are satisfied with the outcomes. It provides a formal closure to the project by ensuring all project work is completed and assessed.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources