Which is a typical core activity within configuration management?

Which is a typical core activity within configuration management?
A . Quality assurance
B . Risk management
C . Verification and audit
D . Progress reporting

Answer: C

Explanation:

Verification and audit is a typical core activity within configuration management according to PRINCE2. This activity involves checking that products meet their requirements and are appropriately approved, and ensuring that all items are correctly accounted for, controlled, and both physically and logically consistent throughout the project lifecycle.

Reference: PRINCE2 Foundation Training Manual, PRINCE2 official website