Which is a type of issue?
A . A lesson
B . A request for change
C . An Exception Report
D . A risk with an estimated high impact
Answer: B
Explanation:
In the PRINCE2 framework, a type of issue that can commonly occur is a request for change. This refers to a proposal for a change or modification to any aspect of the project, which may involve changes to the project’s baseline aspects such as scope, product descriptions, quality criteria, or timeframes.
Reference: PRINCE2 Foundation Training Manual, PRINCE2 official website
Latest PRINCE2 7 Foundation Dumps Valid Version with 463 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund