Which is a true statement about time-driven controls?

Which is a true statement about time-driven controls?
A . Time-driven controls are used for monitoring the progress of Work Packages and management stages
B . Time-driven controls take place when specific events happen
C . Time-driven controls are produced at the end of a stage
D . An Exception Report is a time-driven control

Answer: A

Explanation:

Time-driven controls in PRINCE2® are specifically designed to monitor the progress of Work Packages and management stages at regular intervals. These controls ensure that the project stays on schedule and that any deviations are identified and managed promptly.

Reference: PRINCE2® Foundation official study materials.