Which is a task of product-based planning?

Which is a task of product-based planning?
A . Identify activities and dependencies
B . Write the Project Product Description
C . Prepare the Work Packages
D . Produce Product Status Accounts

Answer: B

Explanation:

A task of product-based planning in PRINCE2® is to write the Project Product Description. This is part of defining and documenting the project’s output, outcome, and benefits, which are crucial for planning the project effectively.