Which is a purpose of the Initiating a Project process?
Which is a purpose of the Initiating a Project process?
A . Decide if it is worthwhile to initiate a project
B . Decide on the project approach
C . Establish solid foundations for a project
D . Identify the number of Work Packages required
Answer: C
Explanation:
The purpose of the Initiating a Project process is to establish solid foundations for the project, ensuring that there is a clear understanding of the reasons for the project, the benefits expected, and how the delivery will be managed. This foundation is crucial for the successful management and delivery of the project.
Reference: PRINCE2 Foundation manual, PRINCE2 official resources