Which is a purpose of the Closing a Project process?

Which is a purpose of the Closing a Project process?
A . Authorize the final stage of the project
B . Confirm that all benefits defined in the Business Case have been achieved
C . Recognize whether objectives set out in the original Project Initiation Documentation have been achieved
D . Delegate day-to-day management of the end of the project to the Project Manager

Answer: C

Explanation:

The purpose of the Closing a Project process is to ensure that the objectives defined in the Project Initiation Documentation (PID) have been achieved. This process involves verifying that the project’s deliverables meet the objectives and that the project has fulfilled its purposes as planned.

Reference: PRINCE2® Foundation official study guide and materials.