Which is a FALSE statement about technical stages?
A . Can overlap with other technical stages
B . Typified by the use a particular set of specialist skills
C . Include the Managing a Stage Boundary process activities
D . Can span more than one management stage
Answer: C
Explanation:
The statement that technical stages include the Managing a Stage Boundary process activities is false. Technical stages refer specifically to the application of skills and techniques during the project delivery process. The Managing a Stage Boundary process is concerned with the end of a management stage and planning the next stage, not directly with technical delivery.
Reference: PRINCE2 Foundation manual, PRINCE2 official resources