Which is a difference between management and technical stages?
A . Management stages require planning and technical stages do not
B . Technical stages can overlap and management stages cannot
C . Management stages deliver products and technical stages do not
D . Technical stages require resources and management stages do not
Answer: B
Explanation:
A key difference between management and technical stages in PRINCE2® is that technical stages can overlap whereas management stages cannot. Technical stages refer to the actual work being done, which can sometimes proceed in parallel, while management stages are concerned with the control and decision points that must be sequential to ensure proper governance.
Reference: PRINCE2® Foundation official documentation and study materials.