Which is a benefit of using PRINCE2?
A . Enables the management of projects as well as of ‘business as usual’ activities
B . Can be tailored by leaving out elements of the method for some projects
C . Can be applied to any type of project
D . Avoids the need to involve corporate or programme management
Answer: C
Explanation:
One of the key benefits of using PRINCE2 is its versatility and adaptability, meaning it can be applied to any type of project across various industries. This flexibility is one of the reasons PRINCE2 is widely adopted globally.
Reference: PRINCE2® Foundation official study materials.