Exam4Training

Which input to the Plan Risk Management process provides information on high-level risks?

Which input to the Plan Risk Management process provides information on high-level risks?
A . Project charter
B. Enterprise environmental factors
C. Stakeholder register
D. Organizational process assets

Answer: A

Latest CAPM Dumps Valid Version with 1089 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Exit mobile version