Which input to the Plan Risk Management process provides information on high-level risks?

Which input to the Plan Risk Management process provides information on high-level risks?
A . Project charter
B . Enterprise environmental factors
C . Stakeholder register
D . Organizational process assets

Answer: A

Latest PMP Dumps Valid Version with 721 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments