Which input to the Manage Stakeholder Engagement process provides guidance on how stakeholders can best be involved in a project?
Which input to the Manage Stakeholder Engagement process provides guidance on how stakeholders can best be involved in a project?
A . Feedback analysis
B . Stakeholder analysis
C . Communication management plan
D . Stakeholder management plan
Answer: D