Which input to the Identify Stakeholders process provides information about internal or external parties related to the project?
Which input to the Identify Stakeholders process provides information about internal or external parties related to the project?
A . Procurement documents
B . Communications plan
C . Project charter
D . Stakeholder register
Answer: C
Latest PMP Dumps Valid Version with 721 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments