Which input to Collect Requirements is used to identify stakeholders who can provide information on requirements?

Which input to Collect Requirements is used to identify stakeholders who can provide information on requirements?
A . Stakeholder register
B . Scope management plan
C . Stakeholder management plan
D . Project charter

Answer: A