Which grid shows which resources are tied to work packages?

Which grid shows which resources are tied to work packages?
A . Work breakdown structure (WBS)
B. Responsibility assignment matrix (RAM)
C. Project assignment chart
D. Personnel assignment matrix

Answer: B