Which function is responsible for ensuring that the Agile Release Train has the Program Vision and Backlog needed to successfully engage in Program Increment Planning?
A . Product Owner
B. Release Train Engineer
C. Product Management
Answer: C
Explanation:
Read more: https://www.scaledagileframework.com/agile-release-train/