Which flow metric is most helpful in indicating when multiple Product Backlog items can be completed? (choose the best answer)
A . Work Item Age.
B. Work in Progress (WIP).
C. Cycle Time.
D. Throughput.
Answer: D
Explanation:
Throughput: The number of work items finished per unit of time. Throughput is the theoretical bandwidth of the team. For example, a team has delivered 10, 8, 12 and 10 Product Backlog items (PBIs) in each of the last 4 Sprints. The average throughput is 10 PBIs per Sprint. So based on historical data, the team can complete 1-10 PBIs in 1 Sprint. 1-15 PBIs in 2 Sprints, and so on. Remember, that ‘can complete’
and ‘will complete’ is different. ‘Will complete’ is absolute where as ‘can complete’ is not and can have dependencies.