Which factor should the project manager have considered when developing the product?
A project manager had to schedule additional planning sessions to add requirements from an international stakeholder. The stakeholder expressed concern about the product not meeting the client’s needs.
Which factor should the project manager have considered when developing the product?
A . Stakeholder’s location
B. Responsibility matrix
C. Stakeholder’s needs
D. Availability of resources
Answer: C
Latest PMP Dumps Valid Version with 721 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments