Which event triggers the issuance of a certificate of occupancy?
A . Construction work is complete except for fire alarm testing.
B . The contractor sends you a pay request for 100% complete work.
C . The owner wants to move into part of the space before the rest is finished.
D . The city inspector has inspected and finalized the job.
Answer: D