Which estimation technique should the project manager implement in this context?
A new project needs to be submitted for urgent funding approval. The project, which will use a new technology, is vital to the organization. The entire Scrum team has worked together for over 3 years on multiple projects and delivered the previous project under the approved budget.
Which estimation technique should the project manager implement in this context?
A . Budget estimate
B. Definitive estimate
C. Story points
D. Order of magnitude
Answer: D