Which estimation technique can be used in Agile project delivery to size the user stories during sprint planning? Please choose the correct answer.
A . Detailed bottom-up effort estimate the breaks each user story up into hours or shorter tasks
B . Relative estimate in ideal person days that reflects the best estimate provided by the project team
C . Detailed bottom-up effort estimate by the SCRUM Master in story points based on the user story complexity
D . Product Owner’s relative estimate of the effort that will be needed to implement the user story
Answer: D
Latest C_ACTIVATE12 Dumps Valid Version with 198 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund