Which estimation technique can be used in agile delivery approach to size the user Stories during sprint planning?
A . Detailed bottom-up effort estimate by the scrum master in story points based on the User story complexity
B . Product owners relative estimate of the effort that will be needed to implement the user story
C . Detailed bottom-up effort estimate that breaks each user story up into hours or shorter tasks
D . Relative estimate in ideal person days that reflects the best estimate provided By the project team
Answer: A
Latest C_ACTIVATE22 Dumps Valid Version with 95 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund