Which elements are used to calculate the due dates defined in service level agreements (SLAs)? Note: There are 2 correct answers to this question.

Which elements are used to calculate the due dates defined in service level agreements (SLAs)? Note: There are 2 correct answers to this question.
A . Maintenance plan
B . Service contract
C . Operating hours
D . Working calendar

Answer: C D