Which earned value management formula can you use to predict how much more will need to be invested in the program based on current program performance?

You are program manager for the HYH Program. Your program governance is requiring you to use earned value management to predict how closely your program is tracking to the cost and schedule baselines and to predict overall program performance.

Which earned value management formula can you use to predict how much more will need to be invested in the program based on current program performance?
A . EV/AC
B . EV/PV
C . BAC/CPI
D . EAC-AC

Answer: D

Latest PgMP Dumps Valid Version with 452 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments