Which does NOT reflect the PRINCE2 principle of continued business justification?
A . There must be a justifiable reason for starting a project
B . The business justification drives decision making
C . If a project is no longer forecast to deliver a financial benefit, it should be stopped.
D . If a project can no longer be justified, it should be stopped
Answer: C
Explanation:
The principle of continued business justification in PRINCE2 means that a project must remain justified throughout its life cycle. The key factor is the project’s ongoing justification, not solely its ability to deliver financial benefits. Projects may continue for reasons other than financial gain, such as strategic importance, compliance, or public safety. Therefore, stopping a project based only on financial criteria does not reflect this principle accurately.
Reference: PRINCE2 Foundation manual, PRINCE2 official resources