Which document will be created to support this activity?
A program manager needs to establish direction and identify the essential aspects of a program. In addition, they must ensure that the context and framework of the program are properly defined, assessed, and documented.
Which document will be created to support this activity?
A . Program resource management plan
B . Program management plan
C . Program master schedule
D . Program scope statement
Answer: B