Which describes a standard change?

Which describes a standard change?
A . A high-risk change that needs very thorough assessment
B . A change that is typically implemented as a service request
C . A change that must be implemented as soon as possible
D . A change that needs to be scheduled, assessed and authorized following a defined process

Answer: B