Exam4Training

Which date is relevant for the calculation for further planned dates for all objects?

The maintenance engineer creates a singel cycle plan with the following parameters:

* the call object is maintenance order

* the indicator or seprate completion of maintenance call date is NOT set

* the indicator for completion requirement is NOT activated

* both shift factors are set to 100% .

Which date is relevant for the calculation for further planned dates for all objects? choose 1 answer
A . planned date of the next call number
B . completion date of maintenance plan
C . technical completion date of the maintenance order
D . basic finish date of the maintenance order

Answer: A

Exit mobile version