You are creating payment terms.
A company processes standard vendor payments on the seventh day of the next month.
You need to set up payment terms for the vendor.
Which date formula should you use?
A . 37D
B . 1M+7D
C . 1M+6D
D . CM+7D
Answer: D
Explanation:
Reference: https://business-central.to-increase.com/md/en-US/ui-enter-date-ranges
Latest MB-800 Dumps Valid Version with 75 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund