You are the planner for a distribution company.
You observe an increase in planned orders for item C0001. You must track the source for these planned orders and break them out based on their demand. You are not concerned with safety stock maximums for this item.
You need to ensure that the master planning batch job will create a unique planned purchase order for every new demand requirement for C0001.
Which coverage code should you use?
A . Manual
B . Period
C . Min/Max
D . Requirement
Answer: D
Explanation:
Explanation: https://docs.microsoft.com/en-us/dynamics365/supply-chain/master-planning/coverage-settings