Which controls can you set when you configure a schedule line category? Note: There are 2 correct answers to this question.
Which controls can you set when you configure a schedule line category? Note: There are 2 correct answers to this question.
A . Create delivery group
B . Delivery relevance
C . Goods movement type
D . Structure scope
Answer: B, C
Explanation:
When configuring a schedule line category, the controls you can set include:
B. Delivery relevance: This determines whether the schedule line and thus the item are relevant for delivery, affecting the generation of delivery documents.
C. Goods movement type: This controls the type of goods movement that will be posted when delivery for items in this schedule line category is executed, impacting inventory management.