A company plans to use master planning in Dynamics 365 Supply Chain Management. The company will sell items between legal entities.
The company has several facilities across legal entities that can manufacture the same products. Same products are produced only in some plants. To meet product demand, when one facility is over capacity, another facility is used to fulfill the downstream demand.
The organizational entities are:
• LegalEntityA: Plant 1.2, and 3
• LegalEntityB: Plant4and 5
• LegalEntityC: Plant 6. 7, and 8
The following plants must be planned together:
• Plant 1. Plant 3. and Plant 4
• Plant 2. Plant 6. and Plant 8
• Plant 5 and Plant 7
You need to configure master planning for the facilities.
Which configuration mechanism should you use?
A . Production groups
B . Item model groups
C . Coverage groups
D . Intercompany planning groups
Answer: D