Which Collect Requirements output links the product requirements to the deliverables that satisfy them?

Which Collect Requirements output links the product requirements to the deliverables that satisfy them?
A . Requirements documentation
B. Requirements traceability matrix
C. Project management plan updates
D. Project documents updates

Answer: B